Britannia Beach Kitchen and Bathroom Renovation
After renting out the lower level of their Ottawa home for years, the family is reclaiming and renovating the space.
Fresh Reno is renovating the kitchen and bathroom, including creating two large openings to connect the kitchen to the rest of the living space, and widening the doorway into a bedroom that is becoming the dining room.
This project is scheduled to take six weeks.

Day 4: The new openings are supported by tripled-up 2x12s laminated with 2 layers of half-inch plywood—as recommended by the structural engineer. The kitchen is much more open now.

Day 6: Electrician Steve Legallez, of Legallez Electric, doing… well the electrical. Steve is the ONLY electrician we work with (this includes in my own home) and he’s excellent.

Day 9: The kitchen and bathroom electrical is complete and the reno passed the Electrical Safety Authority (ESA) electrical rough-in inspection today. Drywall is almost complete.

Day 21: Spring has finally sprung on the final day of March. So, we’re cutting bathroom tiles outside.

Day 20: The counter installers came in to measure. We’ve installed temporary counters and will be back when the permanent counters arrive.
This renovation is nearly complete. Permanent counters have been ordered and we’ll be back when they arrive.