Category Archives: Bathroom

3
Dec
2018

Anik and Tyler’s bedroom-turned-bathroom.

Posted By: Tag: Bathroom | Comments Off on Anik and Tyler’s bedroom-turned-bathroom.

We are turning a bedroom that backs onto the master bathroom into their dream ensuite.

Follow us on FacebookInstagram or Twitter for daily pictures from our renovations.

Day 1 of Anik and Tyler’s renovation. We are turning a bedroom that backs onto the master bathroom into their dream ensuite.
Day 1: The renovation is humming along. We’ve built them an extra closet for the bedroom and installed a pocket door frame.
Day 5: Yes you can convert a bedroom into a bathroom! Electricians from Legallez Electric and plumbers from Penta Plumbing came this week to create the infrastructure. It helps that there’s a water supply to an adjacent bathroom.
Thank you Anik and Tyler! We always, always appreciate snacks
We had a debate about the spelling of a bathroom adjoining a bedroom. Is it ensuite, en-suite or en suit? My word nerd wife got an official ruling on Twitter from James McCarten, editor of Canada’s most venerable journalism guides, the Canadian Press Stylebook and Caps and Spelling.
Day 7: Drywall is up and we’ve started mudding. This is the view from the bedroom into the bathroom.
Day 8: How a shower is born when you turn a bedroom into a bathroom.
Day 9: How a shower is born when you turn a bedroom into a bathroom.
Day 11: Floor tile.
Day 13: Recessed shower shelf in herringbone!
A recessed shower shelf adds a full day of labour.
Day 14: Now THIS is a vanity!  It’s December 19 and we’re waiting for a few ordered pieces to arrive (e.g. doors), so will be back when those arrive. 

Follow us on FacebookInstagram or Twitter for daily pictures from our renovations.

8
Jun
2018

Amber and Nate’s bathroom #2

Posted By: Tag: Bathroom | Comments Off on Amber and Nate’s bathroom #2

We’re renovating two bathrooms at Amber and Nate’s. This is the second.

Follow us on FacebookInstagram or Twitter for daily pictures from our renovations.

Bathroom before.
Bathroom before.
Leonia Silver 12 x 24 tiles for the master bathroom floor.
The recessed shower shelf in Amber and Nate’s first bathroom was a hit. So, we’re doing it again in the master bathroom.
Grouted hex tile shower shelf!
Ikea Godmorgon vanity in walnut.
Here’s why so many people chose the Ikea Godmorgon vanity. Smart plumbing down the back of the vanity so you get full drawers, top and bottom.
Hex detail on the mirror.
Finished shower!

Follow us on FacebookInstagram or Twitter for daily pictures from our renovations.

7
May
2018

Amber and Nate’s bathroom #1

Posted By: Tag: Bathroom | Comments Off on Amber and Nate’s bathroom #1

We’re renovating two bathrooms at Amber and Nate’s house.

Follow us on FacebookInstagram or Twitter for daily pictures from our renovations.

Day 1: Bathroom before.
Day 1: Bathroom before.
Today’s site supervisor is named Eda.
Day 5: The plumbing and electrical are done. After a short drywall sanding shoulder workout we’ll be painting today.
Day 6: bathroom shower tile going in. There will be a three-foot-long recessed shelf. This is “Enigma” tile from Home Depot, 6 x 36 Brushed Oak Ash.
Day 8: recessed shower shelf in herringbone tile.
Thanks Amber and Nate! We’re always happy to help.
Bathroom done!
Bathroom done!
Thanks Amber and Nate! Very thoughtful of you.

Follow us on FacebookInstagram or Twitter for daily pictures from our renovations.

19
May
2017

Sarah and Rob’s Basement Renovation

We first met Rob and Sarah while renovating their bathroom in 2015. They asked us back to renovate their basement.

Rob and Sarah’s basement day 1: File this under shocking things we see. That I-beam is holding up the house. Not the best spot to cut an opening for a door.

Day 01 Support beam interrupted with circle

Day 5: Framing almost finished. Dricore done. Electrical done (Salter Electrical). Plumbers are coming on Monday (Penta Plumbing) and spray foam insulation crew (O’Reilly Brothers) is coming on Tuesday.

Day 05 Fresh Reno Ottawa Renovation Contractor basement renovation framing nepean kanata barrhaven manotick

Day 10: Turning that awkward support post into an area for symmetrical built-in shelves.

Day 10 Fresh Reno Ottawa renovation contractor basement support post

Oh YUM. Thanks Rob and Sarah!

Day 15 Chocolates from Spain

Day 19: tiled the bathroom shower with 12″ x 24″ Pasha Collection tiles from Home Depot.

Day 19 Fresh Reno Ottawa renovation contractor basement bathroom nepean barrhaven kanata Pasha Collection tiles

Day 20: Drop ceiling the clients purchased from Costco.

Day 20 Fresh Reno Ottawa renovation contractor Basement ceiling

Day 22: hidden electrical panel and shoe storage.

Day 22 Fresh Reno Ottawa renovation contractor basement hide electrical panel shoe storage

Day 23: The basement is finished!

Day 23 Fresh Reno Ottawa renovation contractor basement nepean 1 Day 23 Fresh Reno Ottawa renovation contractor basement nepean 2 Day 23 Fresh Reno Ottawa renovation contractor basement nepean 3 Day 23 Fresh Reno Ottawa renovation contractor basement nepean 4 Day 23 Fresh Reno Ottawa renovation contractor basement nepean 5 Day 23 Fresh Reno Ottawa renovation contractor basement nepean 6

19
May
2017

Kelley and Phil’s Kanata Bathroom Renovation

Posted By: Tag: Bathroom | Comments Off on Kelley and Phil’s Kanata Bathroom Renovation

Day 1: Bathroom before demolition:

Day 01 Fresh Reno Ottawa renovation contractor bathroom before kanata Day 01 Fresh Reno Ottawa renovation contractor kanata bathroom before

Day 6: The plumbing is done, tub is installed, and the tiles are going up today. Traffic Master “mushroom” tile from Home Depot.

Day 06 Fresh Reno Ottawa renovation contractor bathroom tile nepean kanata barrhaven

Picking up: Picking up the bathroom Ikea Godmorgon vanity, sink and faucets.
HELLO ICE CREAM!

Day 9 Fresh Reno Ottawa renovation contractor bathroom picking up ikea vanity

Day 11: Bathroom is done!

Day 11 Fresh Reno Ottawa renovation contractor bathroom ikea godmorgon vanity sink cabinet

Best toothbrush holder EVER.

Day 11 Fresh Reno Ottawa renovation contractor storm trooper toothbrush holder

Finished shower. Shower head and controllers from Hudson Reed.

Day 11 Fresh Reno Ottawa renovation contractor Hudson Reed shower

Yesssss THIS Star Wars shower curtain.

Day 11 Fresh Reno Ottawa renovation contractor star wars shower curtain

So thoughtful! A thank you card and Tim Hortons gift certificate.

Day 11 Fresh Reno Ottawa renovation contractor storm Thank You

19
Dec
2016

Michelle and Bert’s Basement and Bathroom Renovation

Posted By: Tag: Basement, Bathroom | Comments Off on Michelle and Bert’s Basement and Bathroom Renovation

That moment when you know you are really REALLY going to like this client.

Day 01 Fresh Reno Ottawa renovation contractor baking promises

Day 1: Demolishing the old basement was a family-friendly event.

Day 01 Fresh Reno Ottawa demolition.JPG

Day 1: the demolished basement.

Day 01 Fresh Reno Ottawa demolition basement

Day 12: Framing, electrical, plumbing rough-in, and spray foam insulation are complete. Just waiting for drywall to be delivered.

Day 12 Fresh Reno Ottawa renovation contractor manotick kanata nepean spray foam basement insulation

Homemade fudge!!! Thanks Michelle and Bert.

Day 12 Fresh Reno Ottawa fudge

Day 16: And then there was a bathroom! Drywall, tub, plumbing and all.

Day 16 Fresh Reno Ottawa renovation contractor basement bathroom barrhaven nepean kanata manotick

Clients who bake for us are EVERYTHING.
Thanks Michelle and Bert!

Michelle and Bert baking

Day 20: Sanding drywall all morning and we’re only two thirds done. Can’t feel my shoulders.

Day 20 Fresh Reno Ottawa renoation contractor basement drywall nepean manotick barrhaven

Day 23: The walls are painted and it’s starting to look like a finished space. Next we’ll be laying the heated flooring and tile in the new bathroom.

Day 23 Fresh Reno Ottawa renovation contractor basement manotick nepean kanata barrhaven

The walls are painted Benjamin Moore “Edgecomb Gray”.

Day 23 Fresh Reno Ottawa renovation contractor basement paint

Day 24: Ditra Heat system installed on the bathroom floor. Now we tile.

Day 24 Fresh Reno Ottawa renovation contractor basement bathroom Ditra Heat system nepean barrhaven kanata manotick

Day 25: Shower tile under way. 3×12 subway with Ardesia mosaic.

Day 23 Fresh Reno Ottawa renovation contractor bathroom tile subway ardesia mosaic

Day 29: Chalet laminate from Alexanian going in.

Day 29 Fresh Reno Ottawa renovation contractor Chalet laminate from Alexanian basement

Day 34: Finishing touches. Bi-fold doors for the under-stair storage and the laundry-craft room.

Day 37 Fresh Reno Ottawa renovation contractor basement bathroom nepean 4

Day 37: finished bathroom!

Day 37 Fresh Reno Ottawa renovation contractor basement bathroom nepean 1

Day 37 Fresh Reno Ottawa renovation contractor basement bathroom nepean 2

Finished basement!

Day 37 Fresh Reno Ottawa renovation contractor reviews

Day 37 Fresh Reno Ottawa renovation contractor basement bathroom nepean 3

10
Dec
2016

Chantal and Evan’s Basement

These are possibly my favourite before pictures EVER.

Bathroom before:

Day 01 Fresh Reno Ottawa renovation contractor bathroom before

Basement before:

Day 01 Fresh Reno renovation contractor before

Day 9: The self-levelling compound, Dricore floor, framing and drywalling is done. Today is the final day of drywall mudding. Tomorrow we sand the walls. So basically an epic shoulder workout.

Day 09 Fresh Reno Ottawa renovation contractor basement renovation kanata barrhaven nepean manotick

Day 10: Sand Dune Pebble mosaic tile on the shower base.

Day 10 Fresh Reno Ottawa renovation contractor nepean barrhaven kanata manotick

Day 12: Laying laminate floor.

Day 12 Fresh Reno Ottawa renovation contractor Home Decorations Collections laminate nepean barrhaven kanata manotick

Day 13: Venetian Stone wall tile being installed in the shower.

Day 13 Fresh Reno Ottawa renovation contractor shower tile basement nepean barrhaven kanata manotick

The basement is done!

Day 16 Twitter Fresh Reno Ottawa renovation contractor basement bathroom nepean barrhaven kanata manotick 3 Day 16 Twitter Fresh Reno Ottawa renovation contractor basement bathroom nepean barrhaven kanata manotick 2 Day 16 Twitter Fresh Reno Ottawa renovation contractor basement bathroom nepean barrhaven kanata manotick 1

 

20
Jul
2016

Alex and Janine’s basement kitchen and bathroom

Alex and Janine recently moved to Ottawa. We worked on their plans long-distance and it all came together so well.

Ripley looooooves to play tug with his octopus. (We started a new bathroom and kitchenette reno this week, but know you'd much rather see pictures of the dog than an empty space.)

Ripley looooooves to play tug with his octopus. (We started a new bathroom and kitchenette reno this week, but know you’d much rather see pictures of the dog than an empty space.)

Day four: We've created a basement bathroom where there wasn't one. Brought in licensed plumbers and electricians. Next up is the city inspection (which we always pass).

Day four: We’ve created a basement bathroom where there wasn’t one. Brought in licensed plumbers and electricians. Next up is the city inspection (which we always pass).

ottawa renovation renovator contractor basement kitchen bathroom nepean barrhaven kanata manotick

Day 4: Basement kitchenette where there was previously a blank space.

You will give me the banana, Don.

You will give me the banana, Don.

Renovation renovator basement ottawa kitchen bathroom nepean barrhaven kanata manotick

Basement bathroom day 9: Floor tiles are going down. 12×24 “enigma” tiles from Home Depot. Paint is ‘Frozen Pond’ by Behr.

Basement reno day 11: Subway tile installed for the kitchenette backsplash. The basement will be finished this week.

Basement reno day 11: Subway tile installed for the kitchenette backsplash. The basement will be finished this week.

Day 14: Alex and Janine's basement renovation is done!

Day 14: Alex and Janine’s basement renovation is done!

Day 14: Alex and Janine's basement renovation is done!

Day 14: Alex and Janine’s basement renovation is done!

19
May
2016

Karen’s South Ottawa Bathroom

Posted By: Tag: Bathroom | Comments Off on Karen’s South Ottawa Bathroom

Karen never liked her bathroom. It’s as simple as that.

Fresh Reno Ottawa renovation contractor bathroom nepean barrhaven manotick kanata

Bathroom Before.

Fresh Reno Ottawa renovation contractor bathroom nepean barrhaven manotick kanata

Bathroom Before

Fresh Reno Ottawa renovation contractor bathroom mosaic tile nepean barrhaven kanata manotick

Day 5: tiling the shower. Tiles from Home Depot. Karen made a great choice! She referred to the mosaic tiles as ‘bling’.

Day 13: Bathroom done. The tub is an Aerosens jet tub.

Day 13: Bathroom done. The tub is an Aerosens jet tub.

Day 13: Bathroom done. The vanity was a special order from Home Depot.

Day 13: Bathroom done. The vanity was a special order from Home Depot.

Day 13 Fresh Reno Ottawa renovation contractor shower mosaic manotick nepean kanata barrhaven

4
Aug
2015

Katie and Joe’s Ottawa Bathroom Renovation

Posted By: Tag: Bathroom | Comments Off on Katie and Joe’s Ottawa Bathroom Renovation

It’s rare that we’re surprised, but sometimes the “before” can still take our breath away.
You’ve actually been USING this shower?

Day 1: shower before.

Day 1: shower before.

We’re told this is the husband’s bathroom. We haven’t ask what he did so wrong that he needs to use this room.

Day 1 bathroom before.

Oh YUM. Thank you, Katie, for the cookies.

Oh YUM. Thank you, Katie, for the cookies.

Day 5: Tiling the shower. Joe is a tall man, so we ensured that the plumber put the shower head plumbing up high.

Day 5: Tiling the shower. Joe is a tall man, so we ensured that the plumber put the shower head plumbing up high.

Day 6: Schluter Ditra floor heat system to take the chill off the tile floor.

Day 6: Schluter Ditra floor heat system to take the chill off the tile floor.

Day 7: Sherwin Williams Colonnade Grey paint.

Day 7: Sherwin Williams Colonnade Grey paint.

Day 8: Wood effect floor tiles.

Day 8: Wood effect floor tiles.

Done! Katie and Joe's bathroom is complete.

Done! Katie and Joe’s bathroom is complete.

Done! Katie and Joe's bathroom is complete.

Done! Katie and Joe’s bathroom is complete.