Roy and Robert’s Kitchen

Posted By: Tag: Kitchen | Comments Off on Roy and Robert’s Kitchen

Day 1: Old kitchen during demolition.

Day 1: Old kitchen during demolition.

Day 5: Electrical is done and painting is nearly done. Today we put down Mohawk Antique Sable vinyl floor from Lowes.

Day 5: Electrical is done and painting is nearly done. Today we put down Mohawk Antique Sable vinyl floor from Lowes.

Day 6: Ikea cupboards going in.

Day 6: Ikea cupboards going in.

Day 8. This is quickly coming together! And check out how they're using that under-the-stairs space as a pantry. We've put on a temporary counter until the permanent counter arrives in several weeks.

Day 8. This is quickly coming together! And check out how they’re using that under-the-stairs space as a pantry. We’ve put on a temporary counter until the permanent counter arrives in several weeks.

The quartz counter arrived! We went back to tile the backplash and connect the appliances. The kitchen is done!

The quartz counter arrived! We went back to tile the backplash and connect the appliances. The kitchen is done!

The kitchen is done!

The kitchen is done!

The kitchen is done!

The kitchen is done!